Claims and Management under FIDIC Standards

Claims and Management under FIDIC Standards

Claims management plays a vital role in preserving project budgets, schedules, and contractual balance in the intricate world of international construction. The International Federation of Consulting Engineers created the FIDIC Conditions of Contract, which offer a thorough and methodical approach to managing claims with a focus on prompt notification, documentation, and unbiased resolution.

The FIDIC contracts’ structured claim management process is covered in detail in this blog, along with important requirements, dispute procedures, benefits and drawbacks, typical claim situations, difficulties, and tactics for effectively avoiding and resolving claims.

What is a Claim Under FIDIC?

A formal request for relief, compensation, or entitlement made by one party to the other due to a situation or event that impacts the performance of contractual obligations is known as a claim under the FIDIC Conditions of Contract. This might entail:

Extra time to finish the project (also known as an extension of time, or EOT)

Extra money to cover unanticipated expenses

Depending on the event’s impact and nature, either or both

FIDIC contracts specify precise procedures for the notification, validation, and settlement of claims (specifically in Clause 20 of the 1999 edition and Clause 20 & 21 in the 2017 edition).

Types of Claims Under FIDIC

FIDIC broadly categorizes claims into two primary types:

1. Contractor’s Claim
These are allegations made by the contractor, typically as a result of:

Postpone the project’s advancement

Raise the cost of construction

Impose extra requirements that weren’t anticipated at the time of tendering

Common Grounds for Contractor’s Claims:

Cause Relevant FIDIC Clause Typical Claim
Employer’s delay or default Clause 8.4, 1.9, 13.1 Extension of Time (EOT), cost for idle resources
Unforeseeable physical conditions Clause 4.12 Time and cost relief for unexpected ground conditions
Variations Clause 13 Cost + EOT for additional scope
Force Majeure / Exceptional Events Clause 19 (1999) / Clause 18 (2017) EOT, possibly cost if not excluded
Delay in approvals or instructions Clause 1.9, Clause 8.1 EOT, cost escalation due to decision delays

Examples of Claims Made by Contractors:
Example 1: Drawing Approvals Are Delayed
The contractor is awaiting updated structural drawings. They file a claim under Clauses 8.4 and 1.9 for idle labor costs and 14 days of EOT.

Example 2: Unexpected Ground Situations
The contractor comes across unexpected rock strata while excavating. Clause 4.12 is used to make a claim for the extra expenses of rock excavation and EOT.

Example 3: Divergences in Purview
The drainage layout is altered per the engineer’s instructions. In order to implement the updated design, the contractor files a claim under Clause 13.3 for $50,000 and 10 days EOT.

2. Employer’s Claims

The employer filed these claims, usually as a result of:

Delays or defaults by the contractor

Failure to adhere to the requirements

Property or work damage

Other violations of the contract

Common Grounds for Employer’s Claims:

Cause Relevant FIDIC Clause Typical Claim
Contractor’s delay Clause 8.7 Liquidated Damages (LD) for delay
Defective work/materials Clause 7.5 Cost of rectification or deduction from payment
Contractor’s failure to complete Clause 15.2 Termination, recovery of completion costs
Damage to property or people Clause 17 Claim for indemnity or insurance

Examples of Claims Made by the Employer:
Example 1: Completion Delay
The contractor doesn’t finish by the due date. Clause 8.7 allows the employer to deduct $10,000 for each week of delay.

Example 2: Electrical installations that are flawed
Inspections conducted after handover show non-compliant wiring. Clause 7.5 allows the employer to claim remedial costs.

Example 3: Inability to Advance Work
Progress is not consistently maintained by the contractor. After giving notice in accordance with Clause 15.1, the employer ultimately ends the agreement and deducts the re-engagement expenses from the contractor’s performance security.

Key Differences: Contractor vs Employer Claims

Aspect Contractor’s Claim Employer’s Claim
Who initiates? Contractor Employer
Common basis Delays, additional costs, variations, unforeseen events Delay damages, defects, breach of contract
Objective To gain time/money/relief To recover costs or enforce compliance
Managed by Clause 20 (Claims Procedure) Clause 2.5 (1999) or Clause 20.2 (2017)
Dispute path Engineer → DAAB → Arbitration Engineer → DAAB → Arbitration

Key Aspects of FIDIC Claim Management

1. Timely Notice (Clause 20.1)
The need for prompt notification is one of the cornerstones of FIDIC claim management. Within 28 days of learning (or should have learned) of the incident or situation giving rise to a claim, the contractor is required to notify the engineer. The possible financial or contractual ramifications should be mentioned in this written notice. If the contractor doesn’t meet this deadline, they risk losing their entitlement unless they can demonstrate that there were extraordinary circumstances that warranted the notification delay. This provision guarantees proactive handling of claims and early notification of possible problems to all parties.

2. Submission of a Detailed Claim
The contractor has 42 days from the date of the event or circumstance (or as agreed with the engineer) to submit a fully detailed claim after the initial notice. This submission needs to contain:

A thorough explanation of the situation or event

The claim’s contractual foundation

supporting documentation, facts, and evidence

A precise estimate of the financial impact and/or time extension

This stage guarantees that statements are supported by factual analysis and documentation rather than being ambiguous or conjectural, allowing the engineer to fairly evaluate them.

3. Timeline for the Engineer’s Response
The engineer has 42 days from the date of submission of the detailed claim to reply. The engineer’s job is to objectively assess the claim and either:

Give your full or partial approval to the claim.

Give reasons to refute the assertion.

Ask for more information or supporting documentation.

In addition to guaranteeing that the contractor receives a decision on time, this structured timeline encourages efficiency and accountability in the claims assessment process.

4. Provisional Claims for Continued Occurrences
FIDIC permits contractors to file interim claims on a monthly basis for events that have long-lasting impacts, like protracted inclement weather, political upheaval, or a protracted delay in site access. These claims track the overall cost or delay over time and are cumulative. The contractor is required to submit a final consolidated claim that summarizes the entire impact after the event’s effects have subsided. Instead of waiting until the project is finished, this method enables continuous disruptions to be documented and paid out gradually.

5. Pathway for Dispute Resolution
The FIDIC contract specifies a multi-tier dispute resolution pathway in the event that the claim cannot be settled by the Engineer’s decision or if one of the parties is unhappy with the result:

In order to swiftly settle disputes, the Dispute Avoidance/Adjudication Board (DAAB), a standing or ad hoc body of impartial experts, renders legally binding but not final decisions.

Amicable Settlement: A mandatory 28-day negotiation period is offered to settle the disagreement amicably before it escalates further if either party is unhappy with the DAAB’s ruling.

International Arbitration: If a friendly resolution is not possible, the matter is taken to international arbitration, which is governed by the contract and frequently by ICC rules. The arbitrator’s ruling is final and enforceable.

This tiered system maintains the contractor’s right to seek legal remedies while offering several avenues for resolution if necessary.

Common Claim Scenarios Under FIDIC

Scenario Cause Relevant FIDIC Clause Typical Resolution
Extension of Time (EOT) Claim Weather delays, late approvals, force majeure Clause 8.4 Notify, submit claim, Engineer reviews; possible DAAB escalation
Additional Cost Claim Inflation, site access delays, scope changes Clause 13, Clause 4.12 Claim with cost breakdown and evidence; may involve Engineer/DAAB
Employer’s Delay or Instruction Late drawing approvals, delayed site access Clause 1.9, Clause 13.1 Contractor submits EOT/cost claim; Engineer determines entitlement
Unforeseen Ground Conditions Unexpected soil or water table issues Clause 4.12 Notice + geological evidence; Engineer evaluates and grants relief
Disruption due to Variations Multiple scope changes affect sequencing Clause 13.3 Submit claim with delay impact analysis; Engineer or DAAB reviews
Late or Incomplete Payments Disputes on interim certification Clause 14.7 Engineer must clarify; unresolved issues go to DAAB or arbitration